The year 2018

Ségou: The foundation of the school building has been created

This is the most difficult and time-consuming part of the construction and it's the most expensive part of the construction.

Ségou: Two machines for the production of bricks are available

The bricks for the school building are produced locally. April 2018

Ségou: 80,000 bricks for school construction

The first bricks are produced. A total amount of 80,000 pieces are needed. May 2018

Ségou: The work of the bricklayers begins

The building becomes visible. August 2018

Ségou: Progress of construction

The outer walls are built. September 2018

Ségou: Le bâtiment de l'école en développement

The walls for the first part of the school are complete. November 2018